Guiding the establishment and management of construction machine costs under actual construction conditions, the Ministry of Construction has issued Document No. 2032 / BXD-KTXD to Vietnam Geotechnical Joint Stock Company with the following contents: According to the regulations of the State at the time of signing the contract on guiding the method of determining the price of machine and equipment for construction work (Article 3, Chapter 2, Circular 06/2010 / TT-BXD dated 26 The contents of the cost of the machine shift (including depreciation costs, repair costs, fuel costs, energy, machine operator wages, costs other machine) is determined according to the types of machines used for construction of works and specific conditions of the works.

The annual depreciation rate is determined according to the principle of suitability with the economic life of the machine and the life of each type of machine in the works. The number of years shall be determined on the principle of compatibility with the characteristics and operating procedures of each type of machine, the work volume of the work, the work size, construction tempo and other concrete conditions.

Compared with the content stated in Document No. 334/2017-GEOVN dated 12/3/2017 of Geotechnical Vietnam Joint Stock Company, if the design drawing construction, approved construction methods have been assigned Specify the required operating procedures of continuous vacuum pumps 3 shifts per day, the number of hours specified in the shift is 8 consecutive hours (the rest stop, preparation, maintenance ... are done outside hours of machines). The number of backup machines is 10%, to ensure that there are always enough machines to maintain the vacuum pressure required by the design. At the same time, the construction unit has complied with the above requirements and has been checked and taken over by the project management units, the actual depreciation rate of the pumps used for the works shall be determined. Determined on the basis of the ratio of the number of machine shifts to the actual work and the number of shifts in the whole life of the machine.

The actual number of operating hours of a pump is determined on the basis of the project acceptance records, the construction work logbook, the statistics on the number of pumps, the life of the machine, the rules Determining and requesting technical time for maintenance and repair of machines ... The number of life-cycle operations shall be determined according to the depreciation duration prescribed by the Ministry of Finance.

In order to accurately determine the actual depreciation rate of the pump used for the project, the parties may hire qualified consultant organizations to perform the calculation.

The payment, settlement and adjustment of construction contract prices must be made according to the contents of the contracts signed between the parties and in accordance with the law provisions applicable to the contract and not contrary to the invitation dossiers. brass.

 

 

 